Open PermitsWhat is the name of your state? NY Buyer's title company says we have open permits on garage and fireplace. What does this mean, what do I need to do to resolve and how long does that normally take? |
|
#2
| |||
| |||
| it means a permit was pulled for intended work and nobody ever called the inspector to inspect the work and give his "ok" on the work. Call the building inspector to do a final inspection on whatever work was being done so he can sign off on the work performed. In my area, it would take less than a week to do this.
__________________ we are all born ignorant. It is when one fails to remedy that ignorance when they become aware of that ignorance when one proves themselves, simply, they are just plain old fashioned; dumb. |
|
#3
| |||
| |||
| Hopefully the work was done to code and will not need to be corrected.
__________________ Adoptive parents ARE "real" parents. Sharing genes is not what makes you a "parent"! |
|
#4
| |||
| |||
| This may end up easily resolved or it may get ugly. |
![]() |