What is the name of your state? NY
I'm in contract for $500K for a new construction of a summer house - started March, 2004 - contract states the builder will complete the project by Sept, 2004 with an absolute deadline of Dec, 2004. It's now April, 2004 and house is only 75% complete. I've already paid $400K. There is no penalty clause specified in the contract for being late on the completion. I probably will be able to complete the job with another contractor with the remaining $100K.
What steps should I take in getting out of the contract with the current builder or to pressure him to finish the job? BTW, I'm still on cordial terms with the builder.
Any advice on this is greatly appreciated.
Thanks...RN
I'm in contract for $500K for a new construction of a summer house - started March, 2004 - contract states the builder will complete the project by Sept, 2004 with an absolute deadline of Dec, 2004. It's now April, 2004 and house is only 75% complete. I've already paid $400K. There is no penalty clause specified in the contract for being late on the completion. I probably will be able to complete the job with another contractor with the remaining $100K.
What steps should I take in getting out of the contract with the current builder or to pressure him to finish the job? BTW, I'm still on cordial terms with the builder.
Any advice on this is greatly appreciated.
Thanks...RN