PleaseHelp1975
New member
I have a contract with a builder. The contract was pretty solid and included detailed aspects of the job, price and most importantly a firm (not estimated as I crossed out the word estimated before everyone signed) end date. That end date has now passed and there is still a great deal of work left. The builder also structured payments so I paid too much up front (lesson learned( so the cost of the work left is far greater than what is still owed.
I would prefer to just work out an extension but I assume if needed I would be able to hire a new contractor and sue for the additional cost over the original contract for the remaining work, plus time for additional rent and legal fees. Is that a fair assumption?
If I offer an extension I want to incorporate a $ penalty past a certain date to be paid to me weekly as well as change the payment plan for the remaining payments so the payment schedule ties in with the remaining items that need to be done. Since the original contract ended that is within my rights to change the payment schedule correct?
I would prefer to just work out an extension but I assume if needed I would be able to hire a new contractor and sue for the additional cost over the original contract for the remaining work, plus time for additional rent and legal fees. Is that a fair assumption?
If I offer an extension I want to incorporate a $ penalty past a certain date to be paid to me weekly as well as change the payment plan for the remaining payments so the payment schedule ties in with the remaining items that need to be done. Since the original contract ended that is within my rights to change the payment schedule correct?