We hired a contractor to remodel a room. He was given 50% up front with the assurance that the project would be completed by 7/9/2018, it is not completed yet.
There are still issuers with the plumbing,electrical, drywall and trim work. I’d say the project is 50-75% complete so far. My problem is it wasn’t completed when he said it would be and now he hasn’t shown up for 13 days.
What are my legal options for firing him? I don’t recall signing any contract at the time of payment.